- PPAP is the evidence pack proving a supplier can consistently produce parts meeting requirements at the quoted rate.
- There are five submission levels; level 3 is the common default and level 1 is a warrant only.
- The significant production run requirement is what makes PPAP meaningful: parts must come from a real run, not a demonstration.
PPAP parts must come from production tooling, at production rate, over a defined run, commonly 300 consecutive parts. Submitting parts from a short trial defeats the purpose and is the usual reason a submission is rejected.
The eighteen elements
- Design records, and any authorised engineering changes.
- Customer engineering approval where required.
- Design FMEA and Process FMEA.
- Process flow diagram.
- Control plan.
- Measurement system analysis studies.
- Dimensional results and material or performance test results.
- Initial process studies, showing capability.
- Qualified laboratory documentation.
- Appearance approval report where appearance is a requirement.
- Sample production parts and a master sample.
- Checking aids.
- Customer-specific requirements.
- Part Submission Warrant.
The five levels
- Level 1. Warrant only, plus appearance approval where relevant.
- Level 2. Warrant with product samples and limited supporting data.
- Level 3. Warrant with samples and complete supporting data. The usual default.
- Level 4. Warrant plus whatever the customer specifically defines.
- Level 5. Warrant with samples and complete data, reviewed at the supplier's site.
Getting approved first time
- Confirm the level and any customer-specific requirements in writing before you start.
- Run the significant production run properly. This is the element most often compromised under schedule pressure.
- Make sure MSA is complete before dimensional results, because a poor gauge invalidates the measurements.
- Check that the control plan matches the process FMEA and the process flow. Inconsistency between the three is a frequent rejection reason.
- Have the initial process study show capability against the specified characteristics, not against a convenient subset.
After approval
Approval binds you to the process you submitted. Changing tooling, subcontractor, material source or location requires notification and usually resubmission. Quietly changing a process after PPAP is a serious finding in any audit and, more practically, is how field failures start.
PPAP outside automotive
The framework travels well. Aerospace has its own equivalents, and many general manufacturers adopt a simplified PPAP for new parts because the discipline of proving a process before releasing it applies regardless of sector.